Thursday, February 23, 2012

programming

Following my visit to Glenhaven and Avalon; I began the programming process of designing the new office; along with partner Raul Garcia.

We actually have very similar resolutions for space. Here are a few facts we must consider while planning the space.

PRELIMINARY BUILDING PROGRAM
CNNC - CENTER FOR NEW NORTH CAROLINIANS
TYPE OF SPACE exist facilities # of spaces sf/spc NASF
Staff Offices
staff office w/ privacy door 5 120 600
staff office with w/ partitions 5 120 600
Support Staff Office w/ Child’s corner 3 170 510
reception area 1 110 110
Subtotal 14 520 1820
Private Space
Male Toilet Room 1 100 100
Female Toilet Room 1 300 300
Sm Conference Room 1 150 150
Lg Conference Room 1 400 400
Subtotal 4 950 950
Communal Area
Kitchen 1 200 200
Copy / Mail Room 1 110 110
Art Display 1 100 100
Lounge Area 1 220 220
Subtotal 4 630 630
TOTALS 22 2100 3400